Painted, getting trimmed, getting closer....


This pic shows the incomplete outside but you can see the rusted wainscoting, the rough board siding...All interior walls have been painted and trim is going in. The biggest challenge awaiting is the cement floor. After removing some pretty imposing hydrolic lift hardware and patching the openings, our contractor will be grinding and polishing the floors to get that distressed but smmoooth and useful surface.
PIMBY has continued to work on the installation details for the solar PV array. The electrcian is installing fixtures, outlets and switches next week. We may slide in for the May 15 target date, but my guess is this project will have its straggling bits push that date out a week or two. Stop by the site any time you are in for a coffee at Hypno.

No comments: